Butt Fusion welding checklist

Butt Fusion welding checklist
  • Trim the pipe ends all the way around
  • Clean the heater plates
  • When clamping the pipes in place, use the clamps to re-round the pipes
  • Correct procedure: Ask for evidence of recent, random weld inspections by your supervisors

Pressure

  1. Measure the drag pressure
  2. Check the right fusion pressure
  3. Add the two together for the overall pressure setting

Temperature

  1. Set the right heater place temperature (usually in the reange of 200-240C
  2. Give enough heat soak time for the pipe ends to fully heat up
  3. Keep dwell time down so the pipe ends don’t cool before contact

Alighnment

  1. Aim for less than 1mm misalignment
  2. For thicker pipes, misalignment must not exceed 10% of the pipe wall thickness (e.g. for 18mm thick pipe, no more thatn 1.8mm)

When you need focused help fast, get it from a supplier whose success is
keeping your plant moving. Call Advanced Piping Systems now on 1300 792 879

Related Articles

Quick guide to Poly Buttwelding Parameter Calculator (Single Low Pressure)

Buttwelding is the most common type of welding process used to join High-Density Polyethylene (HDPE) pipes and fittings. The process involves the joining of two …

How to prevent wear on your PE pipeline’s bends

Fittings

When it comes to wear prevention, the approach that you take will vary from someone else’s. It comes down to the use case for your …

The coupling or the installation? – the definitive guide

Training

The coupling or the installation? This checklist will help you determine the root cause of a failed coupling. Proper fitting: Is it centralised on the …

How to reduce a flange size while maintaining a consistent pipeline ID

Maxi stub flanges — comprising a hybrid stub flange and backing ring — are a quick and effective solution to reduce a flange size whilst …